WSDOT announced multiple highway closures affecting Puyallup residents starting August 24. Northbound I-405 will close up to two lanes nightly from 9 p.m. to 5 a.m. through August 26. A second closure on I-405 will close up to three lanes from 11 p.m. Friday, August 28, to 4 a.m. Monday, August 31. The HOV lane on southbound I-405 will close nightly from 9:30 p.m. to 5 a.m. through August 28. Northbound I-5 will close three left lanes nightly from 9 p.m. to 5 a.m. through August 26. SR 9 near Kalloch Road will be reduced to a single lane until September 14 for fish passage construction. Residents should expect delays and plan travel around these closures. WSDOT provides a project webpage for more details. Detours will be signed for the I-405 closures.

πŸ“„ Source: WSDOT β€” Highway Construction & Closures β€” https://wsdot.wa.gov/travel/road-construction
Source receipts12 of 16 claims supported Β· 75%

Legacy automated check: the original source text was not preserved. These earlier verdicts have not passed the current publication checks and may contain errors. Source: original document β†—

  • ⚠
    WSDOT announced multiple highway closures affecting Puyallup residentsNo usable supporting receipt β€” unverified.
  • βœ“
    The highway closures will start on August 24β€œ405: Up to two lanes of northbound I-405 from I-5 (milepost 0) to milepost 1.5 will be closed nightly, 9 p.m. Monday, Aug. 24 – 5 a.m. Wednesday, Aug. 26.”
  • βœ“
    Northbound I-405 will close up to two lanes nightly from 9 p.m. to 5 a.m.β€œ405: Up to two lanes of northbound I-405 from I-5 (milepost 0) to milepost 1.5 will be closed nightly, 9 p.m. Monday, Aug. 24 – 5 a.m. Wednesday, Aug. 26.”
  • ⚠
    The closure of Northbound I-4305 will last through August 26No usable supporting receipt β€” unverified.
  • βœ“
    A second closure on I-405 will close up to three lanes from 11 p.m. Friday, August 28β€œ405: Up to three lanes of northbound I-405 will close from the Northeast 85th Street on-ramp to Northeast 100th Street from 11 p.m. Friday Aug. 28 to 4 a.m. Monday, Aug. 31. A signed detour will be in place.”
  • βœ“
    The second closure on I-405 will end on 4 a.m. Monday, August 31β€œ405: Up to three lanes of northbound I-405 will close from the Northeast 85th Street on-ramp to Northeast 100th Street from 11 p.m. Friday Aug. 28 to 4 a.m. Monday, Aug. 31. A signed detour will be in place.”
  • βœ“
    The HOV lane on southbound I-405 will close nightly from 9:30 p.m. to 5 a.m.β€œ405: The HOV lane of southbound I-405 from SR 181 (milepost 1) to I-5 (milepost 0) will be closed nightly, 9:30 p.m. Monday, Aug. 24 – 5 a.m. Friday, Aug. 28.”
  • βœ“
    The HOV lane closure on southbound I-405 will last through August 28β€œ405: The HOV lane of southbound I-405 from SR 181 (milepost 1) to I-5 (milepost 0) will be closed nightly, 9:30 p.m. Monday, Aug. 24 – 5 a.m. Friday, Aug. 28.”
  • βœ“
    Northbound I-5 will close three left lanes nightly from 9 p.m. to 5 a.m.β€œ005: Nightly from 9 p.m. to 5 a.m. the next day beginning Monday, Aug. 24 to 5 a.m. Wednesday, Aug. 26, three left lanes of northbound Interstate 5 will close from State Route 526/State Route 527 (milepost 189) to Lowell Road (milepost 191) for maintenance.”
  • βœ“
    The closure of Northbound I-5 will last through August 26β€œ005: Nightly from 9 p.m. to 5 a.m. the next day beginning Monday, Aug. 24 to 5 a.m. Wednesday, Aug. 26, three left lanes of northbound Interstate 5 will close from State Route 526/State Route 527 (milepost 189) to Lowell Road (milepost 191) for maintenance.”
  • βœ“
    SR 9 near Kalloch Road will be reduced to a single lane until September 14β€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction.”
  • βœ“
    The reduction of SR 9 near Kalloch Road is for fish passage constructionβ€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction. Expect delays in the area.”
  • ⚠
    Residents should expect delaysNo usable supporting receipt β€” unverified.
  • ⚠
    Residents should plan travel around the closuresNo usable supporting receipt β€” unverified.
  • βœ“
    WSDOT provides a project webpage for more detailsβ€œMore information on the <a href="https://wsdot.wa.gov/construction-planning/search-projects/sr-9-unnamed-tributaries-nookachamps-hansen-creeks-fish-passage">project webpage</a>.”
  • βœ“
    Detours will be signed for the I-405 closuresβ€œA signed detour will be in place.”